M/S Mirza Chauki Highways Private Limited

Key Dates

Key Dates

Authority National Highway Authority of India
Concessionaire
M/S Mirza Chauki Highways Private Limited
EPC Contractor
DCC Infra Projects Limited
Independent Engineer
Geo Designs & Research (P) Ltd.
Name of Project
4 laning of NH-33 (old NH-80) section of Mirza Chauki to Frakka section from existing km 190.00 to design km 200.75 km (junction at km 3.100 of NH 133B) and from existing km 260.00 to existing km 283.00 (design km 274.33) in the state of Jharkhand (package-II) on Hybrid Annuity Mode.
Construction Period
730 days, Maintenance Period, 15 years from PC/CC
Maintenance Period
15 years
Project Length
24.883 Km.
Bid Project Cost
Rs. 404 Cr.
Physical Progress
Appointed Date Not declared yet
Financial Progress
Appointed Date Not declared yet
Project Milestone No./Financial Progress
1st @20% (150 Days)
2nd @35% (330 Days)
3rd @75% (510 Days)
Schedule Completion date @100% (730 Days) / 404 Cr.
Scheduled Milestone date
Appointed Date Not declared yet
Payment Milestone
@ 4% of Adjusted BPC on the achievement of Physical Progress @ 5%, 10%, 20%, 30%, 40%, 50%, 60%, 70%, 80% & 90%.